The switchboard will be delivered to site in separate sections on a Hiab lorry; the lorry will park as close as is practical to the switchroom door.
The lorry driver will off load the separate sections of switchgear using the Hiab crane.
In order to move the panels into the switchroom the panels will be laid on their side and moved manually into the switchroom.
Temporary doors may restrict access into the switchroom; if this is the case, the client is to arrange for the doors to be removed whilst the switchboard sections are installed.
The heaviest section of switchgear weighs approx 600 kg and therefore a mobile lifting frame with block and tackle will be employed to return the sections to an upright position.
Once in position the panels will be sited in the position to be identified by the client’s engineer.
The erection of the panel will be carried out in accordance with the manufactures recommendations.
After completion of the erection testing will be carried out in accordance with the manufactures recommendations.
|